Daily works log · day 37
Regional road rebuild, phase 2
Public contract · site manager T. Claeys
“…dry, fourteen degrees. Crew of six, two excavators, a hundred and twenty metres of sewer laid. At kilometre 2.4 a utility line that wasn’t on the plans, so the manhole moves three metres…”
-
Works logDay 37
Weather, crew, machinery and progress
Dry · 6 crew · 2 excavators · 120 m sewer
-
DeviationRecord ready
Manhole moved 3 m, km 2.4
Utility line not on plan · record with photo
-
Follow-up1 open
Utility company: have the line marked